Here we are at the end of week one at a two-storey extension in Heighington.
We’ve demolished an existing garage and utility to make space for a new garage utility with a large bedroom, en-suite, and dressing room on the first floor. I’ll post updates as the project progresses.
Further photos | Here we are at the end of week 5, having lost 8 working days due to the weather.
The first-floor ceiling joists are installed and nearly ready for the roof.